Donald Trump claimed force majeure in 2008 for the non-payment of a $334.2m construction loan to Deutsche Bank.
Donald Trump claimed force majeure in 2008 for the non-payment of a $334.2m construction loan to Deutsche Bank.

Collaboration is key in property disputes



Last week, the people of Haiti suffered a terrible natural disaster. If I were buying or selling a new building there that had been turned to rubble, it would be classified by the lawyers as a force majeure event. Last week also saw a property developer inform its buyers in an off-plan project in Dubai that a force majeure event had taken place, right here in the UAE. In doing so it was relieving itself of all obligations under contract with the buyers and would not be continuing with the building works for which they had paid.

As you may know force majeure is French for "superior force" and is readily found in contracts freeing both parties from liability or obligation when an event beyond their control takes place and so prevents either party from completing their obligations under the contract. A force majeure event may be war, strike, riot, crime or what in legal parlance is termed an "act of God", such as a natural disaster.

This particular UAE-based developer has blamed the global financial crisis as an event beyond its control and so invoked force majeure. In November 2008, Donald Trump tried the same strategy. He blamed the world financial crisis for the non-payment of a US$334.2 million (Dh$1.22 billion) construction loan to Deutsche Bank. The jury is still out on that one. The developer in question has a project consisting of 5 million square feet of sellable area, of which 50 per cent has been sold at an original price of Dh2,000 per sq ft. It has collected 30 per cent from customers, or Dh1.5bn, in receivables. It is extremely unlikely that customers will see any of their money returned since the majority of it has been spent in infrastructure and sub-structure works. The developer by contract did what it was supposed to do: it used the funds for building the project. Unfortunately it is impossible for the developer to complete the project because further receivables from customers will not be forthcoming. Neither is bank financing available and, most critically of all, there is an oversupply of units in the market that will last for a long time to come.

Before you draw your daggers and make for the developer's office, there is one thing I have not told you. This particular developer was a sub-developer within a master development owned by a master developer, and it is the latter that stopped all works and demobilised its contractors. So the sub-developer in question may have collected a massive amount from buyers and used it legitimately on the project, but it cannot continue because the master developer has effectively shut down the entire site.

By closing shop, the master developer is no longer building out the infrastructure - roads, pipes, electricity - or signing off design approvals from the sub-developer for the different stages of construction. The sub-developer's hands are tied. So surely the situation is something beyond the control of the sub-developer, but under the contract or the sales and purchase agreement (SPA) signed with the buyer, the sub-developer is directly obligated to the buyer. There is no fallback on the master developer. Yes, there may have been an unwritten convention in the market that the master developer will effectively underwrite all of the sub-developers, but that convention is not in writing and so offers no practical protection for buyers.

That, plus the fact that the master developer is in absentia with buyers, then leaves the sub-developer and the buyer in an extremely difficult position. If we repeat the formula across hundreds of other projects where a sub-developer may go this route, you would need a scientific calculator just to read all of the zeros after the first couple of digits. "What is permitted to be a force majeure event can be the source of much controversy in the negotiation of a contract," says Rima Jameel, a partner at the Dubai-based legal firm Motei and Associates. "For a developer [defendant] to invoke force majeure, the event proposed as force majeure must pass three tests.

"First, externality; the defendant must have nothing to do with the event's happening. Second, unpredictability; if the event could be foreseen, the defendant is obligated to have prepared for it. Being unprepared for a foreseeable event leaves the defendant culpable. This standard is very strictly applied. And finally, irresistibility; the consequences of the event must have been unpreventable. "Although suspension by the master developer constitutes an extraordinary circumstance beyond the control of the sub-developer, if it does not fulfil the three aforementioned elements, it would not ascend to a force majeure event."

Where force majeure is invoked, then the sub-developers' obligation to build and the buyers' obligation to pay ceases until force majeure is remedied. Once the matter is resolved, then the obligation on both parties continues again. Most SPAs will outline what should happen in terms of the obligations under a force majeure event, and for how long an event can continue. A contract will normally allow for between six months and one year, but will depend on circumstance.

If the force majeure period delays completion beyond the completion plus overrun date, where does that leave the buyer? According to Ms Jameel, the SPA should clearly state the consequences and entitle either party to terminate, should the event continue for a specified period of time. Otherwise she refers to Article 273 of the UAE Civil Code (Federal Law No. 5 of 1985), which she says provides that if in a "mutual binding contract, an obligation is discharged because of impossibility of performance, all other counter obligations shall discharge and the contract shall then be automatically rescinded".

But she says that this relates only to that part of the contract that is impossible to perform, and so the discharge of obligation also only relates to that part. She adds: "These provisions also apply in continuing contracts to the temporary impossibility of performance. And the creditor [buyer] may in these cases rescind the contract after serving notice upon the debtor [seller]. In this case, pursuant to Article 274 of the UAE Civil Code, the creditor is to be put back in the position he was in prior to entering into the contract."

Although one sub-developer has started down this track and others may follow, the law certainly appears to protect buyers. It is much more sensible for both seller and buyer to collaboratively work out a situation in which both parties can be discharged of their obligation towards one another in dead-end projects, without making it too onerous on either side. There will definitely be some pain, but it should be limited through the use of the right surgical instruments available in the law.

Rehan Khan is a consultant and writer based in Dubai

Europe’s rearming plan
  • Suspend strict budget rules to allow member countries to step up defence spending
  • Create new "instrument" providing €150 billion of loans to member countries for defence investment
  • Use the existing EU budget to direct more funds towards defence-related investment
  • Engage the bloc's European Investment Bank to drop limits on lending to defence firms
  • Create a savings and investments union to help companies access capital
Recent winners

2002 Giselle Khoury (Colombia)

2004 Nathalie Nasralla (France)

2005 Catherine Abboud (Oceania)

2007 Grace Bijjani  (Mexico)

2008 Carina El-Keddissi (Brazil)

2009 Sara Mansour (Brazil)

2010 Daniella Rahme (Australia)

2011 Maria Farah (Canada)

2012 Cynthia Moukarzel (Kuwait)

2013 Layla Yarak (Australia)              

2014 Lia Saad  (UAE)

2015 Cynthia Farah (Australia)

2016 Yosmely Massaad (Venezuela)

2017 Dima Safi (Ivory Coast)

2018 Rachel Younan (Australia)

Mercer, the investment consulting arm of US services company Marsh & McLennan, expects its wealth division to at least double its assets under management (AUM) in the Middle East as wealth in the region continues to grow despite economic headwinds, a company official said.

Mercer Wealth, which globally has $160 billion in AUM, plans to boost its AUM in the region to $2-$3bn in the next 2-3 years from the present $1bn, said Yasir AbuShaban, a Dubai-based principal with Mercer Wealth.

Within the next two to three years, we are looking at reaching $2 to $3 billion as a conservative estimate and we do see an opportunity to do so,” said Mr AbuShaban.

Mercer does not directly make investments, but allocates clients’ money they have discretion to, to professional asset managers. They also provide advice to clients.

“We have buying power. We can negotiate on their (client’s) behalf with asset managers to provide them lower fees than they otherwise would have to get on their own,” he added.

Mercer Wealth’s clients include sovereign wealth funds, family offices, and insurance companies among others.

From its office in Dubai, Mercer also looks after Africa, India and Turkey, where they also see opportunity for growth.

Wealth creation in Middle East and Africa (MEA) grew 8.5 per cent to $8.1 trillion last year from $7.5tn in 2015, higher than last year’s global average of 6 per cent and the second-highest growth in a region after Asia-Pacific which grew 9.9 per cent, according to consultancy Boston Consulting Group (BCG). In the region, where wealth grew just 1.9 per cent in 2015 compared with 2014, a pickup in oil prices has helped in wealth generation.

BCG is forecasting MEA wealth will rise to $12tn by 2021, growing at an annual average of 8 per cent.

Drivers of wealth generation in the region will be split evenly between new wealth creation and growth of performance of existing assets, according to BCG.

Another general trend in the region is clients’ looking for a comprehensive approach to investing, according to Mr AbuShaban.

“Institutional investors or some of the families are seeing a slowdown in the available capital they have to invest and in that sense they are looking at optimizing the way they manage their portfolios and making sure they are not investing haphazardly and different parts of their investment are working together,” said Mr AbuShaban.

Some clients also have a higher appetite for risk, given the low interest-rate environment that does not provide enough yield for some institutional investors. These clients are keen to invest in illiquid assets, such as private equity and infrastructure.

“What we have seen is a desire for higher returns in what has been a low-return environment specifically in various fixed income or bonds,” he said.

“In this environment, we have seen a de facto increase in the risk that clients are taking in things like illiquid investments, private equity investments, infrastructure and private debt, those kind of investments were higher illiquidity results in incrementally higher returns.”

The Abu Dhabi Investment Authority, one of the largest sovereign wealth funds, said in its 2016 report that has gradually increased its exposure in direct private equity and private credit transactions, mainly in Asian markets and especially in China and India. The authority’s private equity department focused on structured equities owing to “their defensive characteristics.”

Gulf Under 19s final

Dubai College A 50-12 Dubai College B

RESULT

Argentina 0 Croatia 3
Croatia: 
Rebic (53'), Modric (80'), Rakitic (90' 1)